Groundworks 

 

 

Written by greavesie on 2009-12-24

 

 

Gentlemen and the occassional Lady,
 
As discussed at committee recently I have now produced the list of external groundworks that need to be completed by the second week of April 2010. You will see that it is not possible for me to do all this work and run my business and prepare the playing surfaces and keep my wife happy at home. (and maybe have a pint or seven)
To this end I have produced a Schedule of Works and need people to agree to take on small parts of this work and ensure they are completed on time. Myself , Mark Maskell, Bobby and Brian will be able to assist you in sourcing any materials required and will set out exactly what is to be done,( I am sure Bobby, as pavilion manager, has some interior works he will relate as well.)  All you need to do is spend a little of your time putting something back into YOUR club. I would like to see a meaningful contribution from ALL players who represent the club at senior level. Let's start 2010 in a positive and organized way, as a team!
 
Simply email me with the number of the job you wish to volunteer for I will add you to the list. This is the current up-dated list.
 
Wishing us all a happy and successful cricketing 2010.
 
Greavesie.
 
 
External works required for 2010.
 
The re-furbishment of the covers. To include.....
 
JOB 1... Repair of jointing strips. Simon Greaves
JOB 2... Checking of all wheels and repairing as neccesary.
JOB 3... Re-fixing edges of covers to improve performance. Dave Wolverson   Keith Poulter
JOB 4... Replacement of numerous broken gutter brackets and joints. Dave Wolverson   Keith Poulter
JOB 5... Repair of cover material with "Duck Tape" from underneath. Dave Wolverson   Keith Poulter
JOB 6... Fitting of new "Hoselock" couplings to facilitate easy use of hoses. Dave Wolverson   Keith Poulter
 
The completion of the new Scorebox/Storage facility. To include....
 
JOB 7... Painting of fascia and barge-boards in Buckingham Green exterior gloss.
JOB 8... Painting of frontage in Semi-gloss black. 2 people
JOB 9... Painting of interior in White Vinyl Silk emulsion.  Adam Morris  Neil Morris
JOB 10... The treating of all exterior weatherboard with stain to match decking fencing. 2 people
JOB 11... Wiring of lighting and power from consumer. Brian O'Brien
 
The re-furbishment of the sight-screens. To include....
 
JOB 12... Painting the base of sight-screen that is already complete. Andy Sandford   Lewis Mundy
JOB 13... Construction of other sight-screen to same specification. Simon Greaves
JOB 14... Painting all timber work on sight-screen that is not PVC. Andy Sandford   Lewis Mundy
JOB 15... Checking and repairing wheels as required.
 
The re-furbishment of boundary rope. To include....
 
JOB 16... Removing and replacing damaged rope from winder. Pete Harrison
JOB 17... Repair of tyre.
 
Protection of deck area. To include....
 
JOB 18... Cleaning of decking and application of deck treatment. 2 people
JOB 19... Repair and oiling of all deck furniture. Clive Wale
JOB 20... Removal and storage of umbrella. Mark Maskell
JOB 21... Treating of fencing and ballustade to match scorebox. 2 people
 
Small works to pavilion exterior. To include....
 
JOB 22... Spot repairs to white ballustrade. (filling and painting) Rich Pettifer
JOB 23... Painting of soffit above deck area.
JOB 24... Fitting of soffit above entrance porch.
JOB 25... Decoration of soffit above porch. Roger Potgieter
JOB 26... Restaining of side door. Roger Potgieter
JOB 27... Fixing of ballustrade to wall next to side door. Simon Greaves
JOB 28... Replace missing bricks on ramp side. Mark Maskell
 

Completion of exterior lighting. To include....
 
JOB 29... Fixing of bollard light. Brian O'Brien
JOB 30... Completion of cable trench. 2 people
JOB 31... Re-instating all ground works to accept overseeding. 2 people